New World Blenheim Alterations

Client:

Ashley and Melanie Shore – Owners New World Blenheim

Project Typology:

Commercial Alteration

Build Timeframe:

15 Months

Date Completed:

2020

Significant Stats:

Minor extension, re-modelling and earthquake strengthening. New structural steel bracing, new insitu wall to East wall of building. Seismic upgrade included new staircase, and external precast panel walls. Large sections of the old precast panels were pulled out and replaced with new shopfront glazing. New drainage pipework and electrical conduits installed throughout existing shop.

0

Floor Area (m 2)

0

Height (m)

Challenges:

Working within an existing operating supermarket. Areas were fenced off in four stages, with temporary bridging across excavated trenches. The first stage was during the Christmas period, when the supermarket is extremely busy.

The timing was also during the Covid pandemic, so there was a lockdown, as well as social distancing and additional H&S precautions once work re-commenced.


Success:

Completing two months early, to budget, and to a high standard. There was minimal re-work for all trades.


Proportion of Resources:

Robinson Construction delivered the Overall Project Management, and the traditional Concrete, Carpentry and Finishing trades.

Using subcontractors for Structural Steel, Precast, Electrical, Hydraulic, and Painting.


Key Personnel:

Nick Robinson (Project Manager)

Glyn Hughes (Site Manager)

Gareth Shawcross (QS)


How Key Personnel Supported Success:

2-weekly meetings with Foodstuffs South Island project manager, and as needed with the wider consultant team ensured a very smooth project.


Referee:

Ashley Shore (former owner/operator), Blenheim New World

Email: ashley.shore@newworld-si.co.nz