CPR Coffee Co

Client:

CPR Coffee Co

Project Typology:

Part Demolition and Complete Refurbishment

Build Timeframe:

11 Months

Date Completed:

2020

Significant Stats:

Demolition of external façade, together with internal partitions, floor and ceiling linings stripping the entire interior. Rebuild within the perimeter walls the new structural steel bracing, internal framing, wall and ceiling linings, aluminium windows & doors

0

Floor Area (m 2)

0

Height (m)

Challenges:

Working on a confined CBD site means always ensuring appropriate traffic management is in place when required; and minimising noise, dust and public disturbance.

Ensuring that the existing circa 1940’s building and its construction were brought up to current code.


Success:

Delivering a very high-level finish, bringing new life to an old building.



Proportion of Resources:

Robinson Construction delivered the Overall Project Management, and the traditional Concrete, Carpentry and Finishing trades.

Using subcontractors for Structural Steel, Roofing, Electrical, Hydraulic, Mechanical Services, Joinery and Painting.


Key Personnel:

Mark Watson (Project / Site Manager)

Gareth Shawcross (QS)


How Key Personnel Supported Success:

Communication between our project manager, the client, and consultants was on a regular basis and contributed toward the success of the project.